A350 Westbury Roadworks

September 16, 2019 12:01 AM - October 4, 2019 11:59 PM
Westbury A350

A350 Westbury Roadworks

Wiltshire Council will be closing the A350 through Westbury during September and October to undertake highway resurfacing. Road closures will be required whilst the work is taking place. These road closures will be in place for 24 hour periods to ensure the work is completed quickly and without a drawn out programme.

Phase 1

Work Area 1 A - Between Frogmore Road and Edwards Street

Work Area 1 B - Between Edwards Street and Station Road (B3091)

Phase 2

Work Area 2 A - Between Station Road (B3091) and High Street

Work Area 2 B - Between High Street to approximately 40m before Bratton Road (B3091)

Phase 3

Work Area 3 A - Between approximately 40m before Bratton road (B3091) and Orchard Road

Work Area 3 B - Between Orchard Road and Leigh Road (A3098)

Programme of Works

Geo grid and a groundsurvey works will be undertaken during the night shifts.

Date Location Closure Work
Monday 16 September Phase 1 24 hours Planning off existing surface
Tuesday 17 September

Phase 1

24 Hours Planning existing surface and laying new surface
Wednesday 18 September

Phase 1

24 Hours

Planning existing surface and laying new surface

Thursday 19 September

Phase 1

24 Hours

Laying new surface
Friday 20 September

Phase 1

24 hours

Planning existing surface and laying new surface
Saturday 21 September

Phase 1

24 Hours

Laying new surface

Date Location Closure Work
Sunday 22 September Phase 2 24 hours Laying new surface
Monday 23 September Phase 2 24 hours Planning existing surface and laying new surface
Tuesday 24 September Phase 2 24 hours Planning existing surface and laying new surface
Wednesday 25 September Phase 2 24 hours Laying new surface around ironworks
Date Location Closure Work
Thursday 26 September Phase 3 24 hours Planning existing surface and laying new surface
Friday 27 September Phase 3 24 hours Planning existing surface and laying new surface
Monday 30 September Phase 3 24 hours Laying new surface
Tuesday 1 October Phase 3 24 hours Planning existing surface and laying new surface
Wednesday 2 October Phase 3 24 hours Laying new surface
Thursday 3 October Phase 3 24 hours Installation of new roadmarkings
Date Location Closure Work
4 - 11 October All Phases 24 hours Ironwork readjustment and installation of new lining where required

http://www.wiltshire.gov.uk/highways-improvements-a350-westbury