Here are Wiltshire Council's responses to questions From John Bowley about the money wasted on preparing for the doomed Westbury Eastern Bypass scheme
Question 1 - Is it correct that £5.282 million had previously been set aside for capital expenditure on the now defunct Westbury Bypass scheme?
Response - The budget for 2009/10 for Westbury Bypass was £5.828m assuming the scheme was approved. Approx 90% of this budget would have been funded by the Department for Transport (DfT).
.....................
Question 2 - Is it correct that this £5.282 million has now in effect been a 'saving' which has been used to offset a deficit elsewhere?
Response - No funding will now be received from the DfT. Wiltshire's 2009/10 contribution to the scheme less the closing down costs will be returned back to the County Fund.
.......................
Question 3 - Does the transfer of 'costs' to the revenue account refer to this total figure or to additional costs incurred after cancellation of the scheme? What in-year adjustments are envisaged to the revenue account during 2009-10 to reflect the cessation of the Westbury Bypass project?
Response - The transfer of costs to the revenue account refers to costs incurred by Wiltshire Council previously charged as capital. It is anticipated that the amount will be £4.448 million in 2008/2009 accounts and £0.250 million in the 2009/2010 accounts.
.........................
Question 4 - Please provide a breakdown of the previously proposed capital expenditure on the Westbury Bypass scheme into intended construction cost contribution, fees, other etc.
Response - Expected costs from April 2009 had the scheme gone ahead:
Total scheme cost £34.719m
DfT funding £30.984m
Wiltshire Council contribution £3.735m
DfT funds 50% of preparation costs after scheme approval and 90% of scheme cost.
......................................
Question 5 - Please provide a summary breakdown of costs to date incurred by Wiltshire Council on the Westbury Bypass scheme, inclusive of fees, officer time, relevant other time, planning inquiry expenditure, winding-up costs, contract cancellation fees etc.
Response - Expenditure originally charged to Capital on the Westbury Bypass scheme to 31st March 09 totalled £4.448 million and broken down below. It is anticipated that a further £0.250 million will be incurred during the 2009/10 financial year.
Costs incurred to 31st March 2009:
Highways Consultant Fees £2.838m
Ground Investigations / Hydrological Assessment £0.534m
Other Prof Fees / Surveys / ECI Process / Utilities £0.532m
Compensation to Landowners/Legal costs for inquiry £0.317m
Officer Time £0.184m
Other £0.043m
..............................
Question 6 was about the scheme of delegation.
.............................
Question 7 - What are the costs of the Westbury Station Road railway over-bridge restrictions?
Response - Expected cost approx £70,000 for manufacture and installation of signs (incl. fees) will be funded by Network Rail.
...........................
Question 8 - What is the approximate estimated cost for renovating the Westbury Station Road railway over-bridge for unrestricted full use?
Response - Discussions with Network Rail are in progress to establish the scope and cost of the work required. It will be some time before reliable cost estimates can be given.